At the request of
the client „Pilana Vrata d.o.o." the overhauled system for making glued
laminated timber was put into operation again. The system was previously
controlled by a Siemens S5 PLC and a control panel, however the client did not
have that panel.
With the available documentation and an overview of
the system, the necessary elements for the creation of a new control panel with
an operator panel and communication to the PLC with BCD coding have been
identified. A simulation of the whole process of making glued laminated timber was
made due to the impossibility of connecting to the old Siemens S5 PLC in order
to be able to create the necessary sequences for the proper operation of the
system. After creating the program and a new control panel, the system was
successfully put into operation.